What establishes the construction start date and authorizes construction to begin?

Prepare for the CMAA Certified Associate Construction Manager Exam. Study using flashcards and multiple-choice questions, each with hints and explanations. Ensure your success!

Multiple Choice

What establishes the construction start date and authorizes construction to begin?

Explanation:
The documented signal that marks the official start and gives the contractor permission to begin work is the Notice to Proceed. It comes from the project owner after the contract is in place and any required conditions are met, and it specifies the start date and authorizes mobilization and construction activities. A Letter of Intent shows intent to contract but isn’t a binding authorization to start. A Construction Permit may be required to perform work but does not itself establish the start date or authorize execution. A Bid Invitation is simply the call for bids and does not authorize any construction.

The documented signal that marks the official start and gives the contractor permission to begin work is the Notice to Proceed. It comes from the project owner after the contract is in place and any required conditions are met, and it specifies the start date and authorizes mobilization and construction activities. A Letter of Intent shows intent to contract but isn’t a binding authorization to start. A Construction Permit may be required to perform work but does not itself establish the start date or authorize execution. A Bid Invitation is simply the call for bids and does not authorize any construction.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy