At the ________ estimate stage, the design contingency is generally the ________.

Prepare for the CMAA Certified Associate Construction Manager Exam. Study using flashcards and multiple-choice questions, each with hints and explanations. Ensure your success!

Multiple Choice

At the ________ estimate stage, the design contingency is generally the ________.

Explanation:
The main idea is that early estimates carry the most uncertainty, so the design contingency is the largest when the design is still in its conceptual stage. At this point, the project scope, methods, and costs aren’t well defined, and many unknowns can drive cost changes. As the design progresses through preliminary and design development, more details are resolved, reducing uncertainty, so contingency can be lowered. By the time you reach detailed design, the estimate is more precise and the need for a large design contingency diminishes. That’s why the conceptual stage paired with the highest contingency is the best choice.

The main idea is that early estimates carry the most uncertainty, so the design contingency is the largest when the design is still in its conceptual stage. At this point, the project scope, methods, and costs aren’t well defined, and many unknowns can drive cost changes. As the design progresses through preliminary and design development, more details are resolved, reducing uncertainty, so contingency can be lowered. By the time you reach detailed design, the estimate is more precise and the need for a large design contingency diminishes. That’s why the conceptual stage paired with the highest contingency is the best choice.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy