After a 7-day cylinder strength test shows below the minimum specification, what is the recommended CM action?

Prepare for the CMAA Certified Associate Construction Manager Exam. Study using flashcards and multiple-choice questions, each with hints and explanations. Ensure your success!

Multiple Choice

After a 7-day cylinder strength test shows below the minimum specification, what is the recommended CM action?

Explanation:
When early strength results are below specification, the prudent course is to document what happened, keep close records, and continue to monitor the project while awaiting the full set of later strength tests. A 7-day cylinder reading can be an early indicator, but it doesn’t determine final strength. By recording the result in daily reports and watching the 14-, 28-, and 56-day break results, you gather the data needed to assess overall performance and determine whether adjustments are needed for future placements. In the meantime, review current and upcoming mixes, delivery tickets, and curing procedures to ensure future batches have a higher likelihood of meeting the required strength. Stopping work or notifying the owner is unnecessary unless there’s an immediate safety risk or structural concern. Dismissing the GC team isn’t a constructive or standard corrective action. Increasing the water content would actually reduce strength, not improve it, so it’s not a valid corrective measure.

When early strength results are below specification, the prudent course is to document what happened, keep close records, and continue to monitor the project while awaiting the full set of later strength tests. A 7-day cylinder reading can be an early indicator, but it doesn’t determine final strength. By recording the result in daily reports and watching the 14-, 28-, and 56-day break results, you gather the data needed to assess overall performance and determine whether adjustments are needed for future placements. In the meantime, review current and upcoming mixes, delivery tickets, and curing procedures to ensure future batches have a higher likelihood of meeting the required strength.

Stopping work or notifying the owner is unnecessary unless there’s an immediate safety risk or structural concern. Dismissing the GC team isn’t a constructive or standard corrective action. Increasing the water content would actually reduce strength, not improve it, so it’s not a valid corrective measure.